Monday, December 7, 2009

PV8 - Progress Photos

These photos are taken on the 5th December 2009.

Block B and Block C
Block A and Block D
The roof of Block B and C is completed, while Block A and Block D is still in progress.



4 Storey shoplots near PV8 is almost completed as well.


PV8 - Platinum victory 8 at Taman Melati, Setapak.

PV8 - Stages completed so far

I have received payment advice for the following stages as of December 07, 2009

(a) The work below ground level including piling and foundation of the said building comprising the said building (10%)

(b) The reinforced concrete framework and floor slab of the said parcel (15%)

(c) The walls of the said parcel with door and window frames placed in position (10%)

(d) the roofing/ceiling, electrical wiring, plumbing (without fittings), gas piping (if any) and internal telephone trunking and cabling to the said parcel (10%)

(e) the internal and external plastering of the said parcel (10%)

(f) The sewerage works serving the said building (5%)

(g) the drains serving the said building (5%)

Total of 75% paid including the 10% pay upon signing of S&P Agreement.